Texas halts new data centers as governor calls for audits
AI 中文解读
核心亮点:德州突然踩刹车,暂停所有新建数据中心项目,州长下令严查,因为再不控制,电网就要被AI算力吃垮了。
通俗解读:数据中心是AI和云计算的“大胃王”,又耗电又耗水。以前德州电多、管得松,科技公司都抢着去建,数量仅次于弗吉尼亚州。可现在排队申请接入电网的项目暴增到474吉瓦,是德州电网最高用电量的5倍多,其中九成都是数据中心。这些项目里不少还只是“占坑”的纸上方案,但哪怕只有一小部分真建起来,电网也得崩溃。所以州长不再客气,要求电力部门和电网运营商对每个新项目查电、查水、查噪音、查税收优惠,连业主是谁都要问清楚。
实际影响:对普通人来说,数据中心建多了,抢的是民用电力和水资源,电价已经悄悄涨了,未来还可能继续涨。这项政策若生效,能给德州电网“减负”,避免大规模停电,也防止科技巨头挤占居民资源。但同时也意味着当地数据中心建设会变慢,AI服务、云存储的扩张可能受限,未来某些数字服务的价格或速度或受影响。从中也能看出,AI越火,背后的能源矛盾就越不容忽视。
Tech companies and developers have been scouring the U.S. for places to build data centers, and they’ve been drawn to Texas’s loose regulations and seemingly abundant power supply. Only Virginia hosts more data centers than Texas.
But even Texas can be pushed to the brink. Governor Greg Abbott announced Monday that all new data center projects will need to be audited by both the Public Utility Commission of Texas (PUCT) and the state’s grid operator, the Electric Reliability Council of Texas (ERCOT).
The size of ERCOT’s interconnection queue has grown dramatically this year. In January, ERCOT had 233 gigawatts of projects waiting to connect to its grid. In less than six months, that figure had more than doubled. Today, Abbott’s office said ERCOT is tracking 474 gigawatts of new connection requests. About 90% of those are data centers, according to the grid operator.
Some of those projects are simply paper proposals at this point. Because queues for grid connections have grown so long, the first action many developers take is to get in line. Many projects fizzle out as they progress.
If even a fraction of those proposed projects come to fruition, they could overwhelm the Texas grid. The interconnection queue today represents more than five times ERCOT’s total peak demand.
While many data center operators, including Google and Microsoft, have been drawn to Texas for its ample natural gas reserves, wind and solar have helped ERCOT keep pace with growing electricity demand, according to the Energy Information Administration (EIA). Utility-scale solar capacity grew fourfold between 2021 and 2025. Meanwhile, electricity prices declined over much of that time, according to a report from Amperon.
Electricity prices in Texas are relatively affordable compared with other states, but they have been rising. Data centers and crypto mining facilities have pushed prices higher, according to the EIA.
var playerInstance_jwplayer_6a721715c992c = jwplayer( "jwplayer_6a721715c992c" );
playerInstance_jwplayer_6a721715c992c.setup({
playlist: "https://cdn.jwplayer.com/v2/media/ybaSpcvP",
});
Abbott clearly wants to head off that trend. The governor has directed PUCT and ERCOT to collect a range of information about proposed data centers, including their on- and off-site demand for electricity and water, noise mitigation efforts, light controls, use of tax incentives, and ownership details.
Historically, Texas has favored lighter regulation than many other states when it comes to development. Houston famously lacks a zoning code, and the state has a business-friendly regulatory environment. But data centers have become a flash point across the country, including in Texas. Abbott had previously tried to coax data centers into providing more information through a voluntary survey. Most didn’t respond, so he’s taking a heavier hand to compel compliance.
Depending on what emerges from the audits, Texas’s days as a data center mecca may be coming to a close.