SpaceX won’t remove all of xAI’s unpermitted turbines for another year
AI 中文解读
SpaceX一边说要把孟菲斯数据中心那些没获环保许可的燃气轮机拆掉,一边又宣布要等到2027年7月才全部拆完。这事听起来矛盾,其实背后是AI算力增长和环保监管的正面冲突。这批燃气轮机一直是“临时工”身份,装在拖车上就能绕开审批,但实际排放量惊人,一年能吐出上千吨污染气体,当地已经是全美空气最差的地区之一。SpaceX的辩护理由是“国家安全和能源安全”,司法部也站在它那边,让人觉得有点“大棋局”的味道。更值得玩味的是,它新建的天然气电厂用的涡轮机型号跟现有的完全不同,暗示这些旧设备可能根本不会退役,而是挪去建另一个没公开的项目。对普通人来说,这事最直接的影响就是你呼吸的空气——数据中心要用电,电要烧气,烧气就排烟,只不过这烟主要落在了孟菲斯以南的密西西比州,而AI发展的代价,才刚刚开始有人追问谁来买单。
SpaceX said on Thursday that it will remove the unpermitted turbines powering its xAI data centers near Memphis as it transitions to a permanent, 1.2 gigawatt natural gas power plant.
The turbines won’t be completely removed until July 2027, though. SpaceX said that it’s currently operating 69 gas turbines to power the Colossus data centers, of which many have been operating for months. The NAACP and Southern Environmental Law Center have sued xAI over the use of unpermitted turbines.
SpaceX acquired xAI in February. In its IPO filing, SpaceX said it plans to buy $2.8 billion worth of gas turbines for its data centers over the next three years.
The company claims that it is allowed to operate the existing turbines without permits because they remain on the trailers they were shipped on. But federal regulations say that the turbines xAI has been using, regardless of what they sit on, require permits because of their size and how they’re being used.
The turbines are currently located south of Memphis in Mississippi, just over the border with Tennessee. The region is among the most polluted in the U.S., and xAI has been operating gas turbines that have the potential to emit more than 2,000 tons of smog-forming NOx per year.
Last month, the Department of Justice sided with SpaceX in the NAACP’s lawsuit, saying the unpermitted turbines were a matter of “national, economic, and energy security.”
The new power plant that SpaceX is building will consist of 41 gas turbines ranging in size from 16.48 megawatts to 50 megawatts, according to permit documents issued by the state of Mississippi. They appear to be different from those currently in use, though TechCrunch could not verify the specific models of the 69 existing turbines.
var playerInstance_jwplayer_6a6d57a18c3e3 = jwplayer( "jwplayer_6a6d57a18c3e3" );
playerInstance_jwplayer_6a6d57a18c3e3.setup({
playlist: "https://cdn.jwplayer.com/v2/media/ybaSpcvP",
});
Earlier this year, Elon Musk bought APR Energy, a company that specializes in temporary natural gas power. Based on an archive of the company’s site before it was taken down, the turbines in the company’s fleet also appear to be different from those cited in permits for the new, permanent power plant.
Given that APR Energy’s turbines aren’t likely to be part of the new Colossus power plant, the new turbine fleet is likely intended for another, unannounced project.